Kitchen Renovation (6): The Final Lag and Finish Line!

My excitement was beyond words when the cabinets arrived soon after the dry walls were finished and the tiles laid on the floor. The cabinet installer also started working on the same day. Watching him work, I discovered how exact the task was to ensure that seams and joints were aligned, the hinges on the doors were adjusted and tightened, and the shelves were placed to provide functional partitions. I was very pleased to see the two-tier lazy Susan trays which would give me all the space I had hoped for in the corners of the cabinets.

In the meantime, the painter came in. I had been expecting him for a while, especially the contractor told me that the painter had promised to complete my job before his three-week holiday in Australia. I could simply not bear the thought of my kitchen on hold for three weeks! To my relief, a jovial painter bounced in like a kangaroo (he told me he was Australian), decided on the colour with me and the job was done.

The final lag of the kitchen renovation was a piece of orchestration and co-ordination by the different trades, and the supervisor did a superb job lining them up. Once the lower cabinets had been installed, the countertop person was called in to do the measurements. He used an equipment that was similar to a surveying tool. That was an innovative procedure to me.

1-IMG_1107

It took two weeks for the counter top to be ready. The cabinet installer continued with his work and so did the electrician who put in lighting under and inside some cabinets.

I welcomed the counter top on its day of its arrival like a groom waiting for his bride. I heaved a big sigh of relief when it was brought in, because finally I could tell that it matched my choice of the floor tiles. The backsplash were installed the day after the counter top. Another day for grouting and cleaning up. The last item to go in was the kitchen vent.

I had no idea when I started to post about my kitchen renovation that it had taken some eleven weeks to have everything completed. Not bad, because I was given an estimate of nine to ten weeks when the job started. I had become used to cooking and eating in my make-shift kitchen in the basement, but it’s certainly time I moved to my new kitchen and caryy on. It would take me several days to wipe it down and return to the old routine with new appliances and new storage arrangements . If you were expecting drama from my renovation, you might be disappointed. However, it was an educational experience, nonetheless, finding out the expertise of the different trades and craftsmen, learning to be patient and how to communicate clearly what I wanted using trade terms.

Please don’t ask me about kitchen warming yet; just let me enjoy the sight of it first.

1-IMG_1241

Advertisements

10 thoughts on “Kitchen Renovation (6): The Final Lag and Finish Line!

    1. Opalla Post author

      So true…it’s like a leap of faith into the unknown and what a relief when all this is done. Thanks for your support!

      Reply

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s